Marmont Priory Lock Side Moorings – Refurbishment

The MLC will be carrying out extensive refurbishment of the downstream lock entrance moorings.

Work will commence on 23rd May 2022 and is likely to take around a week to complete. As there will be no place to moor up a boat at this end of the lock during this time a temporary lock keeper will be on hand each day to assist from 8am to 5pm, until the moorings are reopened.